Skyway Professional Centre


Often, when you think of the construction of multi-story medical office buildings, you think of steel as one of the primary materials. And when steel is involved, of course, it adds another layer of complexity to the project, requiring welders and other specialty trades throughout various stages of construction.

For the construction of the four-story Skyway Professional Centre in Red Deer, Alberta Canada, however, that additional complexity was avoided by using RedBuilt’s Red-I Joists throughout each level of the building. Working with Burgess Bredo Architect and Cognidyn Engineering, Timcon Construction developed a schedule and process whereby floor sections were assembled at ground level, including all hangers, and then flown into place by crane.

The result? A job that proceeded smoothly, without any of the delays that can accompany a multi-story project, that followed the schedule set by Timcon, and met all National Building Code of Canada requirements.